Overview
Falcon Heights has identified the Falcon Woods and Northome neighborhoods for rehabilitation as the 2025 Pavement Management Project (Project FH 25-01) which includes:
Falcon Woods Neighborhood (full depth reclamation):
Autumn Street, Prior Avenue N, Summer Street, Moore Street, Howell Street N and Garden Avenue.
Northome Neighborhood (full depth reclamation):
California Ave W, Idaho Ave W, and Iowa Ave W.
The project is proposed to include reconstruction and full depth reclamation of the streets in the Falcon Woods and Northome neighborhoods, paving a new asphalt layer, pathway replacement, storm basin upgrades, spot curb and gutter repair and minor utility work.
Construction Schedule
The contractor’s schedule is shown below. Additional information will be sent out as the contractor is moving to the next phase of their construction.
Please note that the weather will be a factor and the schedule will likely change as the season progresses.
Northome: Substanially Complete. The contractor will be continuing all punch list items (corrections) over the next week.
Falcon Woods: Work within the Falcon Woods neighborhood is substantially complete. The contractor will be continuing all punch list items (corrections) over the next week.
Thank you for your patience during the 2025 PMP project. Notices were sent to all property owners that the City will be conducting the final assessment hearing on October 8 at City Hall at 7:00 PM.
Schedule
The project is scheduled to be bid in the winter of 2025, if approved by council, for construction in the spring/summer of 2025. The tentative project schedule is shown below. Falcon Heights Council actions are noted with “CC”:
|
CC Order of Feasibility Report
|
October 9, 2024
|
|
CC Receive Feasibility Report, Order Public Hearing
|
December 11, 2024
|
| Neighborhood Open House |
January 9, 2025 |
|
CC Public Hearing, Order Plans and Specifications
|
January 22, 2025
|
|
Final Design
|
February 2025
|
|
CC Approve Plans and Order Advertisement for Bids
|
February 26, 2025
|
|
CC Accept Bids
|
April 9, 2025
|
|
Construction
|
Spring/Summer 2025
|
|
Assessment Hearing
|
October 8, 2025
|
|
Final Restoration and Punchlist
|
Spring 2026
|
Funding
This project has the following funding sources from the State, City and property owners along the streets being considered for improvements:
- Storm and sanitary utility funds for repairs needed to the existing utility system;
- Municipal State Aid (MSA) funding through the State of Minnesota’s gas tax;
- Street infrastructure funds; and
- Falcon Heights Special Benefit Assessments levied in accordance with the City’s assessment policy.
Assessments: Falcon Heights’ Assessment Policy calls for assessing 40% of the cost of street improvements typically based on the front footage of adjacent properties. Residential lots will only be assessed for the long side of their property. The estimated assessment roll are available in the 2025 PMP Feasability Report.
Based on the bids received, assessments will be less than the feasibility report: 35.5% lower in the Northome Neighborhood and 34.9% lower in the Falcon Woods neighborhood. The final assessment rate will be calculated based on actual costs.
Project Documents